Page 40 - KBHA Bulletin 10
P. 40

37





                  reasonable. They accepted this extra with a Variation Order on 30 May 1944. They were
                  also issued with a further Variation Order for the demolition of the remaining cottages on

                  site.  This  they  did  as  the  contract  progressed.  The  problem  now  of  finding  alternative
                  accommodation  was  much  reduced  as  the  handover  of  the  first  4  flats  of  Contract  Two

                  commenced  on  2  November  1944,  and  continued  steadily  until  completion  on  22  June

                  1945.  (Fig.  1.17).  The  maintenance-free  period  of  6  months  was  applied  to  the  various
                  handover dates. Another Variation Order was for 460 foot of rough stone walling between

                  the blocks of flats.


                  The subcontractors on the Miller Brothers contract included well known names at that time
                  in  the  building  industry,  two  of  whom  are  still in  business  to  this  day  –  Robertson  and

                  Walton  plumbers  and  Scheltema  &  Co.  roofers.  The  extras  to  this  contract  were  quite

                  considerable  and  totalled  nearly  £4,000  which  included  enlarging  23  kitchens,  adding  a
                  caretaker’s store and office, demolition of old cottages, erecting twenty-seven additional

                  stores  for  gear  in  the  basement  of  the  flats  once  levels  had  been  taken,  adding  further

                  retaining  walls  as  well  as  dividing  walls  between  flats.  The  final  account,  drawn  up  by
                  quantity surveyors Gurney and Hustwick, took over two years to complete as it was further

                  complicated, not only by the extras, but also by the untimely death of the Clerk-of-Works,
                  Mr. Archer, who passed away before completion of the contract.


                  Other costs were also incurred over a gradual period from the completion of Contract Two

                  until 1949. These included the priority of building a children’s playground, especially as

                  letters had been written to Council warning them that they might be held responsible for
                  any motor accident that occurred as the children’s only playground was in the streets, and

                  the  corner  between  Harris  Road  and  Harbour  Road  was  particularly  dangerous.  The
                  Housing Committee were duly instructed to clear an area of burrweed (a stinging type of

                  nettle) and finance was voted for the creation of a playground.
   35   36   37   38   39   40   41   42   43   44   45