Page 151 - Bulletin 18 2014
P. 151

148


               modest  little  masonry  structure,  about  9  metres  high,  which  impounded  2,730  megalitres.

               (Fig.  3.32.)  A  pipeline  64  km  long  delivered  the  water  to  the  Molteno  Reservoir  in
               Oranjezicht above the city. The work was started by a contractor, but he pulled out after a

               few months “due to the difficulties of working in wartime” and the bulk of the work was
               done by a departmental unit led by Stanley Lunn, who would succeed Lloyd-Davies as City

               Engineer.


               The delivery pipeline which in itself was quite a major undertaking, was aligned along the

               original road to Somerset West, through Kuils River, Bellville and the present Voortrekker
               Road  to  the  city.  After  further  severe  water  restrictions  during  the  summer  of  1919-20

               (supply was limited to 4 hours per day), the thirsty city could rejoice when the first Steenbras

               water flowed into the Molteno Reservoir at the end of 1920.


               Lloyd-Davies  and  his  colleagues  had  realised  that  the  little  dam  was  only  a  temporary
               solution to Cape Town's problems. Perhaps it was good handling of the politicians, because

               with  the  ability  to  deliver  now  firmly  established,  it  was  much  easier  to  get  a  positive
               decision out of the Council. Thus in 1926 work began on raising the dam wall. Besides the

               distinguished  Board  of  Engineers,  the  site  staff  included  some  of  the  rising  stars  in  the

               profession: Jack Hawkins, the Resident Engineer would go on to found the well-known firm
               of Hawkins Hawkins and Osborn (invariably known as H20) and a young Ninham Shand was

               his assistant.


               The work was more than a simple raising of the dam wall. By then concrete had become the

               established construction medium, and the entire masonry structure was enveloped by the new
               material.  (Fig.  3.33.)  The  capacity  of  the  reservoir  was  thereby  increased  ten-fold.  An

               additional pipeline was also built across the sandy wastes of the Cape Flats to a new supply
               reservoir at Newlands. Now at last the City Engineer could relax as the new dam could cope

               with the demand for water for another twenty years.


               Other Achievements of Lloyd-Davies


               Lloyd-Davies  had  other  pressing  challenges  apart  from  the  Steenbras  scheme.  There  were

               roads to construct to meet the requirements of modern motor traffic; housing schemes were
               needed to accommodate the poor; and the Southern Suburbs was in dire need of sewerage.
   146   147   148   149   150   151   152   153   154   155   156