Page 72 - Bulletin 18 2014
P. 72

69



               sequence of five slices. Mass concrete, four to five feet thick, was laid down over the top of

               the blockwork as it advanced to make a firm regular working surface that carried the crane
               and trolley tracks. A fresh water main and electric cabling were laid at the same time. The

               process was repeated over and over until completed in December 1918, by which time over
               3,000 blocks (30,000 tons of concrete) had been laid, amounting to perhaps 160 - 200 slices,

               and laid at an average rate of 2 - 3 blocks/day.





               By  the  end  of  1914  the  breakwater  extended  to  302  ft.  and  1,132  blocks  had  been  set.
               Progress  was  slowed  during  1915  by  the  war  and  a  shortage  of  cement  (until  the  war  all

               cement had been imported and now had to be produced locally) and only another 123 ft. were
               added, but it was now past the halfway mark of 391 ft. The cement shortage continued during

               1916 but the structure reached the 562 ft. mark. Rough weather and the worst storm in living
               memory on 13 February also hampered progress.





               The breakwater was to have been terminated in a roundhead but instead it was returned at

               right-angles  for  20  ft.  to  form  a  platform  some  50  ft.  x  30  ft.,  standing  2½  ft.  above

               breakwater  level  and  approached  up  four  steps.  It  was  protected  on  its  sea-side  by  the
               continuation of the parapet wall which was also returned for 28 ft. across the short breakwater

               face. In 1919 a lighthouse was placed at the centre of the return head. It had a two-second
               flash every 20 seconds that was visible from 10 miles out in clear conditions, and a red arc

               covered the sector containing the dangerous reef south of the Breakwater.





               The  breakwater’s  mass  concrete  surface  was  finished  off  with  compressed  asphalt  paving
               slabs.  (Figs.  2.26  –  2.30.)  The  coping  edge  on  the  harbour  side  was  made  of  granolithic

               blocks into which bollards were let at 33 ft. centres for heavier craft to tie up to. Ring bolts in
               between carried life-lines hanging down to water’s edge. Further attention to safety was given

               along the outer wall where life-ladders extending down to spring low water level were fixed
               at three places. Life buoys with life-lines were also attached to the electric light standards on

               the breakwater.
   67   68   69   70   71   72   73   74   75   76   77